HKAA Contract T20M103 – Maintenance Works for Buildings at Midfield Concourse and Airside Ancillary Buildings
Name of Employer: Sun Fook Kong Construction Limited
Date Started: December 2016
Date Completed: December 2019
System:
Plumbing and drainage system
Scaffolding System
Type of Work Performed:
- Routine Maintenance for P&D Work
- Planned Maintenance for P&D Work
- High Pressure Jetting Work in drainage system
- CCTV Inspection Work for drainage system
- Modification works for existing P&D system
- Scaffolding design, erection, maintenance and dismantling completed with CP and form 5