HKAA Contract T21W016 – Modernisation of Air-conditioning System at Terminal 1

Name of Employer: CLPe Solutions

Date Started: June 2022

Date Completed: June 2027

System:

Chilled Water System

Mechanical Ventilation System

Electrical and Control System

Type of Work Performed:

Upgrading the existing AHUs in Terminal 1

  • Replacement of new split / single cooling coils
  • Replacement of traditional belt drive fans with new integrated electronic commutated (EC) fans (retrofit of fan section / fan wall approach), performing optimization, completed with all associated power & signal wiring connection
  • Installation, testing and commissioning of new integrated direct digital controllers (DDCs)
  • Delivery, installation, testing and commissioning of pressure independent control valves (PICVs) and associated flowmeter, modulating control valve, temperature sensors