机管局合约 T21W016 -香港国际机场一号客大楼冷气系统更新工程
Name of Employer: 中电源动
Date Started: 6 月 2022
Date Completed: 6 月 2027
System:
Type of Work Performed:
Upgrading the existing AHUs in Terminal 1
- Replacement of new split / single cooling coils
- Replacement of traditional belt drive fans with new integrated electronic commutated (EC) fans (retrofit of fan section / fan wall approach), performing optimization, completed with all associated power & signal wiring connection
- Installation, testing and commissioning of new integrated direct digital controllers (DDCs)
- Delivery, installation, testing and commissioning of pressure independent control valves (PICVs) and associated flowmeter, modulating control valve, temperature sensors